Solar Panels

SAME-DAY INSPECTIONS ARE NOT AVAILABLE 

Per the solar permit package:

Inspections are typically required to be completed in the following order: 

  1. Footing Inspection (if ground-mounted) 
    *** All 3rd party inspections must be submitted before moving forward *** 
    *** If required, Foundation Survey must be submitted and approved before moving forward *** 
  2. Electrical Ditch Inspection 
  3. Electrical Service Inspection 
    *** If required, Setback Certification must be submitted and approved before moving forward *** 
  4. Electrical Final Inspection

  1. How to Schedule an Inspection

    Inspections must be scheduled through the Community Development Center. In addition to calling to schedule an inspection, the County has a software program that allows contractors and owners to request inspections on-line as well as view inspection results. This service helps get inspections scheduled more quickly and without needing to reach us over the busy phones. For more information, log into the Building Department website.

  2. For Every Inspection

    Your laminated building permit shall be posted in plain view of the right-of-way and the approved set of plans shall be on site. 


If using a 3rd party inspector, the following conditions apply: